Your customer wants to generate costing for internal activities. For which of the following can you define various rates in Activity Type/Price Planning transaction? (Choose three)
The correct answer is A. Plan/actual version B. Cost center C. Period. See the full explanation below for the reasoning.
Question
Your customer wants to generate costing for internal activities. For which of the following can you define various rates in Activity Type/Price Planning transaction? (Choose three)
Options
- APlan/actual version
- BCost center
- CPeriod
- DValue category
- EPlant
How the community answered
(23 responses)- A83% (19)
- D4% (1)
- E13% (3)