When is the latest possible point in time that you can create a settlement rule?
The correct answer is A. Before technical completion. See the full explanation below for the reasoning.
Question
When is the latest possible point in time that you can create a settlement rule?
Options
- ABefore technical completion
- BBefore order release
- CAfter order release
- DAfter technical completion
How the community answered
(43 responses)- A79% (34)
- B7% (3)
- C12% (5)
- D2% (1)