C_TPLM22_67 Question #136: Real Exam Question with Answer & Explanation
The correct answer is D. Loop analysis tool. See the full explanation below for the reasoning.
Question
An activity-relationship-activity path is cyclical and you are not able to schedule the network. Which analysis tool enables you to detect cyclical relationships and correct them? Please choose the correct answer. Response:
Options
- ACycle analysis tool
- BRelationship analysis tool
- CActivity analysis tool
- DLoop analysis tool