SAP
C_TPLM22_67 · Question #135
Which of the following statements concerning requirements grouping are correct? There are 3 correct answers to this question. Response:
The correct answer is A. You can group together requirements for various WBS elements depending on the MRP group B. Grouping together of requirements need not necessarily be carried out on the top WBS element D. Requirements for multiple projects can be combined if certain prerequisites are filled. See the full explanation below for the reasoning.
Question
Which of the following statements concerning requirements grouping are correct? There are 3 correct answers to this question. Response:
Options
- AYou can group together requirements for various WBS elements depending on the MRP group
- BGrouping together of requirements need not necessarily be carried out on the top WBS element
- CRequirements groupings can be used for both evaluated and unevaluated project stocks
- DRequirements for multiple projects can be combined if certain prerequisites are filled
How the community answered
(45 responses)- A82% (37)
- C18% (8)
Community Discussion
No community discussion yet for this question.