Which function allows you to check consistency of the dates within the project structure with or without taking activities into account? Please choose the correct answer. Response:

The correct answer is B. Check dates. See the full explanation below for the reasoning.

Question

Which function allows you to check consistency of the dates within the project structure with or without taking activities into account? Please choose the correct answer. Response:

Options

  • APlanning methods
  • BCheck dates
  • CExtrapolate
  • DSets of dates

How the community answered

(26 responses)
  • A
    15% (4)
  • B
    73% (19)
  • C
    8% (2)
  • D
    4% (1)