Which of the following objects can be generated by a material requirements planning (MRP) run? (Choose two)
The correct answer is B. Purchase requisition E. Planned order. See the full explanation below for the reasoning.
Question
Which of the following objects can be generated by a material requirements planning (MRP) run? (Choose two)
Options
- APurchase order
- BPurchase requisition
- CProduction order
- DSales order
- EPlanned order
How the community answered
(27 responses)- A4% (1)
- B85% (23)
- C4% (1)
- D7% (2)