After which step in the material planning process do you first see planned independent requirements in the stock requirements list?
The correct answer is A. After transferring the sales and operation plan to demand management. See the full explanation below for the reasoning.
Question
After which step in the material planning process do you first see planned independent requirements in the stock requirements list?
Options
- AAfter transferring the sales and operation plan to demand management
- BAfter saving the sales and operation plan
- CAfter saving a sales order
- DAfter processing materials requirements planning
How the community answered
(31 responses)- A81% (25)
- B10% (3)
- C3% (1)
- D6% (2)