A non-stock item is assigned to a plant maintenance order. Which document is generated when the order is released or saved?

The correct answer is A. A purchase requisition. See the full explanation below for the reasoning.

Question

A non-stock item is assigned to a plant maintenance order. Which document is generated when the order is released or saved?

Options

  • AA purchase requisition
  • BA purchase order
  • CA material document
  • DAn inventory reservation

How the community answered

(32 responses)
  • A
    72% (23)
  • B
    16% (5)
  • C
    6% (2)
  • D
    6% (2)