You want to create one bill of material (BOM) to be used for several equipment master records. Therefore, you create a material BOM. In which field do you enter the corresponding material number to…
The correct answer is B. In the Construction Type field. See the full explanation below for the reasoning.
Question
You want to create one bill of material (BOM) to be used for several equipment master records. Therefore, you create a material BOM. In which field do you enter the corresponding material number to assign this material BOM to the equipment master record?
Options
- AIn the Structure Indicator field
- BIn the Construction Type field
- CIn the Order Type field
- DIn the Usage Times field
How the community answered
(56 responses)- A2% (1)
- B80% (45)
- C13% (7)
- D5% (3)
Community Discussion