C_TB1200_10 · Question #39
What ate two activities performed during the realization phase of a well-run SAP Business One implementation project? Note: There are 2 correct answers to this question.
The correct answer is A. Configure and test the system C. Perform a fit/gap analysis. During the Realization phase, the project team translates business requirements into an actual working system - making configuration and fit/gap analysis the two core activities. Option A (Configure and test the system) is correct because Realization is when consultants set up…
Question
What ate two activities performed during the realization phase of a well-run SAP Business One implementation project? Note: There are 2 correct answers to this question.
Options
- AConfigure and test the system
- BManage organizational change
- CPerform a fit/gap analysis
- DAssess business needs
How the community answered
(43 responses)- A81% (35)
- B5% (2)
- D14% (6)
Explanation
During the Realization phase, the project team translates business requirements into an actual working system - making configuration and fit/gap analysis the two core activities. Option A (Configure and test the system) is correct because Realization is when consultants set up SAP Business One to match the company's processes and verify it works through structured testing. Option C (Perform a fit/gap analysis) is correct because this phase involves comparing the standard SAP B1 functionality against the client's specific needs to identify where the system fits and where gaps require workarounds or customization.
Option B (Manage organizational change) is incorrect - while important throughout a project, change management is not a defining activity of the Realization phase itself; it's more prominent in Final Preparation and Go-Live. Option D (Assess business needs) is incorrect because that happens earlier, during the Project Preparation or Business Blueprint phase, before the team begins building anything.
Memory tip: Think of "Realization" as making it real - you're building (configure) and checking (test) the system, and comparing what the software offers to what the business needs (fit/gap). Anything that sounds like planning or discovery (assess needs, change management strategy) belongs to earlier or broader phases.
Topics
Community Discussion
No community discussion yet for this question.