SAP
C_ACTIVATE13 · Question #88
What term is used for a ready-to-run SAP S/4HANA system with pre-built solution Documentation?
The correct answer is A. Best practice system. See the full explanation below for the reasoning.
Question
What term is used for a ready-to-run SAP S/4HANA system with pre-built solution Documentation?
Options
- ABest practice system
- BFully activated appliance
- CSAP model company
- DSAP cloud appliance library
How the community answered
(48 responses)- A75% (36)
- B2% (1)
- C6% (3)
- D17% (8)
Community Discussion