C_ACTIVATE13 · Question #85

Which estimation technique can be used in agile delivery approach to size the user Stories during sprint planning?

The correct answer is D. Relative estimate in ideal person days that reflects the best estimate provided By the project team. See the full explanation below for the reasoning.

Question

Which estimation technique can be used in agile delivery approach to size the user Stories during sprint planning?

Options

  • ADetailed bottom-up effort estimate by the scrum master in story points based on the User story
  • BProduct owners relative estimate of the effort that will be needed to implement the user story
  • CDetailed bottom-up effort estimate that breaks each user story up into hours or shorter tasks
  • DRelative estimate in ideal person days that reflects the best estimate provided By the project team

How the community answered

(41 responses)
  • A
    15% (6)
  • B
    2% (1)
  • C
    5% (2)
  • D
    78% (32)