The correct answer is D. Technical strategy>parameter's hardware>seizing calculation>hardware seizing results>Hardware. See the full explanation below for the reasoning.

Question

What is the order of artifacts within the technical architecture and infrastructure workstream in the prepare phase?

Options

  • ATechnical strategy>hardware specification from hardware vendor>parameters hardware seizing
  • BHardware specification from hardware vendor>parameter's hardware seizing calculation>hardware
  • CHardware specification from hardware vendor>technical strategy>parameter's hardware seizing
  • DTechnical strategy>parameter's hardware>seizing calculation>hardware seizing results>Hardware

Community Discussion

No community discussion yet for this question.

Full C_ACTIVATE13 Practice