nerdexam
SAP

C_ACTIVATE13 · Question #65

C_ACTIVATE13 Question #65: Real Exam Question with Answer & Explanation

The correct answer is B. Product owner. See the full explanation below for the reasoning.

Question

Who determines the tasks that are required to complete the committed backlog items in a sprint?

Options

  • AScrum master
  • BProduct owner
  • CProject manager
  • DProject team

Community Discussion

No community discussion yet for this question.

Full C_ACTIVATE13 Practice