SAP
C_ACTIVATE13 · Question #65
Who determines the tasks that are required to complete the committed backlog items in a sprint?
The correct answer is B. Product owner. See the full explanation below for the reasoning.
Question
Who determines the tasks that are required to complete the committed backlog items in a sprint?
Options
- AScrum master
- BProduct owner
- CProject manager
- DProject team
How the community answered
(26 responses)- A8% (2)
- B77% (20)
- C12% (3)
- D4% (1)
Community Discussion
No community discussion yet for this question.