Who determines the tasks that are required to complete the committed backlog items in a sprint?

The correct answer is B. Product owner. See the full explanation below for the reasoning.

Question

Who determines the tasks that are required to complete the committed backlog items in a sprint?

Options

  • AScrum master
  • BProduct owner
  • CProject manager
  • DProject team

How the community answered

(26 responses)
  • A
    8% (2)
  • B
    77% (20)
  • C
    12% (3)
  • D
    4% (1)