SAP
C_ACTIVATE13 · Question #65
C_ACTIVATE13 Question #65: Real Exam Question with Answer & Explanation
The correct answer is B. Product owner. See the full explanation below for the reasoning.
Question
Who determines the tasks that are required to complete the committed backlog items in a sprint?
Options
- AScrum master
- BProduct owner
- CProject manager
- DProject team
Community Discussion
No community discussion yet for this question.