C_ACTIVATE13 · Question #52

Which activity helps the Project Team add User Stories to the Product Backlog?

The correct answer is C. Conducting the Solution Validation workshop. See the full explanation below for the reasoning.

Question

Which activity helps the Project Team add User Stories to the Product Backlog?

Options

  • AAssessing project risks
  • BPreparing a project schedule
  • CConducting the Solution Validation workshop
  • DPlanning the User Acceptance Test

How the community answered

(69 responses)
  • A
    4% (3)
  • B
    7% (5)
  • C
    74% (51)
  • D
    14% (10)