In which phase should you first run the SAP readiness check for SAP S/4HANA in a "selective data transition" transition path, in a system consolidation scenario that includes conversions from SAP ERP?
The correct answer is A. Explore. See the full explanation below for the reasoning.
Question
In which phase should you first run the SAP readiness check for SAP S/4HANA in a "selective data transition" transition path, in a system consolidation scenario that includes conversions from SAP ERP?
Options
- AExplore
- BDiscover
- CPrepare
- DRealize
How the community answered
(25 responses)- A80% (20)
- B4% (1)
- C4% (1)
- D12% (3)