nerdexam
SAP

C_ACTIVATE13 · Question #27

When does the scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

The correct answer is A. During the sprint review. See the full explanation below for the reasoning.

Question

When does the scrum team receive formal confirmation that the user stories are completed to the satisfaction of the product owner?

Options

  • ADuring the sprint review
  • BDuring the daily scrum meeting
  • CDuring the sprint retrospective
  • DDuring the user acceptance test

How the community answered

(22 responses)
  • A
    82% (18)
  • B
    9% (2)
  • C
    5% (1)
  • D
    5% (1)

Community Discussion

No community discussion yet for this question.

Full C_ACTIVATE13 Practice