Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 correct answers to this question.

The correct answer is B. User acceptance test-plan C. Functional test scenarios. See the full explanation below for the reasoning.

Question

Which artifacts in the testing workstream are created within the realize phase for the "new implementation of SAP S/4HANA Cloud" transition path? There are 2 correct answers to this question.

Options

  • AFunctional specifications
  • BUser acceptance test-plan
  • CFunctional test scenarios
  • DReporting functional specifications

How the community answered

(38 responses)
  • A
    8% (3)
  • B
    79% (30)
  • D
    13% (5)

Community Discussion

No community discussion yet for this question.