SAP
C_ACTIVATE13 · Question #2
What criterion does the product owner use to sequence the product backlog?
The correct answer is C. Business priority. See the full explanation below for the reasoning.
Question
What criterion does the product owner use to sequence the product backlog?
Options
- ARelative effort
- BResource availability
- CBusiness priority
- DComplexity
How the community answered
(37 responses)- A11% (4)
- B5% (2)
- C81% (30)
- D3% (1)
Community Discussion