How would you describe the explore phase in the "new implementation Of SAP S/4HANA cloud" transition path?

The correct answer is B. Solution validation and delta design. See the full explanation below for the reasoning.

Question

How would you describe the explore phase in the "new implementation Of SAP S/4HANA cloud" transition path?

Options

  • ASimplification and custom code impact analysis
  • BSolution validation and delta design
  • CFit-to-standard
  • DSetup and enablement

How the community answered

(27 responses)
  • A
    15% (4)
  • B
    70% (19)
  • C
    11% (3)
  • D
    4% (1)