The correct answer is C. DQAS D. DEV. See the full explanation below for the reasoning.
Question
In the "new implementation of SAP S/4HANA" transition path, which systems are part of the project system landscape? There are 2 correct answers to this question.
Options
- AP-system
- BStarter system
- CDQAS
- DDEV