The correct answer is D. Preventive maintenance options must be set up to auto-generate work orders at the organization. See the full explanation below for the reasoning.

Question

A company has five sites within one organization in their system. They want to activate automatic generation of work orders for three of their sites. Which option can help to achieve this?

Options

  • AWork Orders are automatically generated for each active site.
  • BFrom the Preventive Maintenance application select Generate Work Orders for all Sites.
  • CPreventive maintenance options must be set up to auto-generate work orders at the site level.
  • DPreventive maintenance options must be set up to auto-generate work orders at the organization