C2010-595 · Question #77

Which statement is true when the status changes to INPRG on a work order created from a service request?

The correct answer is B. The status of the associated service request will not be changed. See the full explanation below for the reasoning.

Question

Which statement is true when the status changes to INPRG on a work order created from a service request?

Options

  • AThe actual start date on the service request is updated.
  • BThe status of the associated service request will not be changed.
  • CThe status of the associated service request is changed automatically.
  • DThere is an option to change the status on the associated service request in the Change Status

How the community answered

(21 responses)
  • A
    5% (1)
  • B
    81% (17)
  • C
    10% (2)
  • D
    5% (1)