nerdexam
IBM

C2010-595 · Question #22

The client is using the last completed work order date to trigger a PM generated work order. What type of schedule are they using?

The correct answer is B. floating schedule. See the full explanation below for the reasoning.

Question

The client is using the last completed work order date to trigger a PM generated work order. What type of schedule are they using?

Options

  • Afixed schedule
  • Bfloating schedule
  • Clead time schedule
  • Dtime-meter based schedule

How the community answered

(44 responses)
  • A
    16% (7)
  • B
    73% (32)
  • C
    2% (1)
  • D
    9% (4)

Community Discussion

No community discussion yet for this question.

Full C2010-595 Practice