The client is using the last completed work order date to trigger a PM generated work order. What type of schedule are they using?
The correct answer is B. floating schedule. See the full explanation below for the reasoning.
Question
The client is using the last completed work order date to trigger a PM generated work order. What type of schedule are they using?
Options
- Afixed schedule
- Bfloating schedule
- Clead time schedule
- Dtime-meter based schedule
How the community answered
(44 responses)- A16% (7)
- B73% (32)
- C2% (1)
- D9% (4)