IBM
C2010-555 · Question #92
A fixed-schedule PM needs to be set up. What other setting need to be selected in addition to the frequency value?
The correct answer is C. Use Last Work Order's Start Date to Calculate Next Due Date? checked. quency_schedules.html
Preventive Maintenance
Question
A fixed-schedule PM needs to be set up. What other setting need to be selected in addition to the frequency value?
Options
- AAlert Lead (DAYS) must equal 0
- BAlert Lead (DAYS) must be greater than 0
- CUse Last Work Order's Start Date to Calculate Next Due Date? checked
- DUse Last Work Order's Start Date to Calculate Next Due Date? unchecked
How the community answered
(19 responses)- A5% (1)
- B5% (1)
- C74% (14)
- D16% (3)
Explanation
quency_schedules.html
Topics
#fixed-schedule PM#last work order date#PM frequency#PM configuration
Community Discussion
No community discussion yet for this question.