A fixed-schedule PM needs to be set up. What other setting need to be selected in addition to the frequency value?

The correct answer is C. Use Last Work Order's Start Date to Calculate Next Due Date? checked. quency_schedules.html

Preventive Maintenance

Question

A fixed-schedule PM needs to be set up. What other setting need to be selected in addition to the frequency value?

Options

  • AAlert Lead (DAYS) must equal 0
  • BAlert Lead (DAYS) must be greater than 0
  • CUse Last Work Order's Start Date to Calculate Next Due Date? checked
  • DUse Last Work Order's Start Date to Calculate Next Due Date? unchecked

How the community answered

(19 responses)
  • A
    5% (1)
  • B
    5% (1)
  • C
    74% (14)
  • D
    16% (3)

Explanation

quency_schedules.html

Topics

#fixed-schedule PM#last work order date#PM frequency#PM configuration