IBM
C2010-555 · Question #137
A forecast for a monthly PM has been generated for 6 minutes. A new data has been entered for the second row and saved. When the Process Pending Reforecast button is clicked, the following error…
The correct answer is D. The Reforecast Subsequent Dates? checkbox was not checked before the forecast was. https://www-01.ibm.com/support/docview.wss?uid=swg1IV55903
Preventive Maintenance
Question
A forecast for a monthly PM has been generated for 6 minutes. A new data has been entered for the second row and saved. When the Process Pending Reforecast button is clicked, the following error appears: BMXAT0217E-There is no reforecast pending to process. What would cause this error?
Options
- AThe reforecast dates are locked
- BThe PM is not in the Active status
- CThe reforecast cron task is set to run every 3 days
- DThe Reforecast Subsequent Dates? checkbox was not checked before the forecast was
How the community answered
(24 responses)- A4% (1)
- B8% (2)
- C4% (1)
- D83% (20)
Explanation
Topics
#PM forecast#reforecast#reforecast checkbox#forecast error