nerdexam
IBM

C1000-132 · Question #7

In what Maximo Manage application are the specifications of an asset for calibration entered?

The correct answer is C. Data Sheet Template. In IBM Maximo Manage, the specifications of an asset for calibration are entered in the Data Sheet Template application.

Business Process Configuration

Question

In what Maximo Manage application are the specifications of an asset for calibration entered?

Options

  • AClassifications
  • BAsset
  • CData Sheet Template
  • DImprovements

How the community answered

(49 responses)
  • B
    4% (2)
  • C
    94% (46)
  • D
    2% (1)

Explanation

In IBM Maximo Manage, the specifications of an asset for calibration are entered in the Data Sheet Template application.

Topics

#calibration#data sheet template#asset specifications#meters

Community Discussion

No community discussion yet for this question.