C1000-132 · Question #63

How can a Master Preventive Maintenance record be associated with multiple non-rotating assets?

The correct answer is C. Add the Assets to the Multiple Assets table on the Master Preventive Maintenance record. To associate a Master Preventive Maintenance record with multiple non-rotating assets, we can add the assets to the Multiple Assets table on the Master Preventive Maintenance record. This allows us to associate the preventive maintenance schedule with multiple assets, ensuring…

Business Process Configuration

Question

How can a Master Preventive Maintenance record be associated with multiple non-rotating assets?

Options

  • AUse the Move/Modify Assets action.
  • BUse an Asset Template.
  • CAdd the Assets to the Multiple Assets table on the Master Preventive Maintenance record.
  • DUse the Apply Down Hierarchy action on the Master Preventive Maintenance record.

How the community answered

(41 responses)
  • A
    5% (2)
  • B
    2% (1)
  • C
    90% (37)
  • D
    2% (1)

Explanation

To associate a Master Preventive Maintenance record with multiple non-rotating assets, we can add the assets to the Multiple Assets table on the Master Preventive Maintenance record. This allows us to associate the preventive maintenance schedule with multiple assets, ensuring that the maintenance activities are performed on each of the associated assets as scheduled.

Topics

#Master Preventive Maintenance#Non-rotating Assets#Multiple Assets#PM Association

Community Discussion

No community discussion yet for this question.