IBM
C1000-132 · Question #66
What combination of information on a Work Order is used to create a histogram in the Graphical Scheduling application?
The correct answer is C. Craft Quantity and Hours. Histograms in Graphical Scheduling show the number of resources (Craft Quantity) required vs. the number of hours scheduled.
Business Process Configuration
Question
What combination of information on a Work Order is used to create a histogram in the Graphical Scheduling application?
Options
- ACraft/Skill Level Quantity and Hours
- BLabor and Crew Hours
- CCraft Quantity and Hours
- DCrew Work Group Quantity and Hours
How the community answered
(33 responses)- B3% (1)
- C94% (31)
- D3% (1)
Explanation
Histograms in Graphical Scheduling show the number of resources (Craft Quantity) required vs. the number of hours scheduled.
Topics
#Graphical Scheduling#Histogram#Craft Hours#Resource Planning