In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?
The correct answer is C. the Work Order target start date + the Job Plan duration. In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.
Business Process Configuration
Question
In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?
Options
- Athe Job Plan finish date
- Bthe PM target finish date
- Cthe Work Order target start date + the Job Plan duration
- Dthe Job Plan start date + the Job Plan duration
How the community answered
(16 responses)- A6% (1)
- C94% (15)
Explanation
In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.
Topics
#preventive maintenance#target finish date#work order generation#job plan duration