In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?

The correct answer is C. the Work Order target start date + the Job Plan duration. In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.

Business Process Configuration

Question

In the Work Order Tracking application, a Work Order is generated from a Preventive Maintenance (PM) record. How is the target finish date calculated?

Options

  • Athe Job Plan finish date
  • Bthe PM target finish date
  • Cthe Work Order target start date + the Job Plan duration
  • Dthe Job Plan start date + the Job Plan duration

How the community answered

(16 responses)
  • A
    6% (1)
  • C
    94% (15)

Explanation

In the Work Order Tracking application, when a Work Order is generated from a Preventive Maintenance (PM) record, the target finish date is calculated as the Work Order target start date + the Job Plan duration.

Topics

#preventive maintenance#target finish date#work order generation#job plan duration