In which status can a Job Plan be modified to add a new task?
The correct answer is D. PNDREV. To add a new task or modify a Job Plan that is already active, the Job Plan must first be revised. When revised, the Job Plan status changes to PNDREV (Pending Revision), a draft revision where changes including adding new tasks can be made. After modifications, the revised Job…
Question
In which status can a Job Plan be modified to add a new task?
Options
- ANEW
- BREVISED
- CINACTIVE
- DPNDREV
How the community answered
(51 responses)- A4% (2)
- B8% (4)
- C2% (1)
- D86% (44)
Explanation
To add a new task or modify a Job Plan that is already active, the Job Plan must first be revised. When revised, the Job Plan status changes to PNDREV (Pending Revision), a draft revision where changes including adding new tasks can be made. After modifications, the revised Job Plan is activated, and the previous revision moves to REVISED status and becomes read-only. Job Plans cannot be modified directly when in ACTIVE status; they must be in PNDREV status to allow edits such as adding new tasks.
Topics
Community Discussion
No community discussion yet for this question.