C1000-132 · Question #1
A user wishes to perform the same work tasks on several assets simultaneously. How can this be configured?
The correct answer is D. The Assets should be specified on the Multiple Assets, Locations and CIs table on the Work. If you want to perform the same work task(s) (defined by one Work Order) on multiple Assets at the same time, you should use the Multiple Assets, Locations, and CIs table on the Work Order. This ensures that the same set of planned tasks, job plan, labor, and materials can be…
Question
A user wishes to perform the same work tasks on several assets simultaneously. How can this be configured?
Options
- AA Route should be created with each stop being one Asset and the Job Plan associated with the
- BA Master Job Plan should be created with Tasks for each Asset.
- CA Work Order Hierarchy should be created against the same Job Plan used for all stops.
- DThe Assets should be specified on the Multiple Assets, Locations and CIs table on the Work
How the community answered
(30 responses)- A7% (2)
- B3% (1)
- C10% (3)
- D80% (24)
Explanation
If you want to perform the same work task(s) (defined by one Work Order) on multiple Assets at the same time, you should use the Multiple Assets, Locations, and CIs table on the Work Order. This ensures that the same set of planned tasks, job plan, labor, and materials can be executed across several assets simultaneously, without creating separate routes, hierarchies, or multiple