Which activity belongs to Operational supplier management?

The correct answer is C. determining how quickly alternative workspaces should be available in case of a calamity. Operational supplier management focuses on managing contracts and relationships with external suppliers to ensure service continuity and meet business requirements - including negotiating terms around disaster recovery and business continuity arrangements. Option C fits because…

Operation Management

Question

Which activity belongs to Operational supplier management?

Options

  • Ainstalling a software package on a workstation
  • Bimproving the performance of application software
  • Cdetermining how quickly alternative workspaces should be available in case of a calamity

How the community answered

(34 responses)
  • A
    15% (5)
  • B
    6% (2)
  • C
    79% (27)

Explanation

Operational supplier management focuses on managing contracts and relationships with external suppliers to ensure service continuity and meet business requirements - including negotiating terms around disaster recovery and business continuity arrangements. Option C fits because defining how quickly a supplier must provide alternative workspaces after a calamity is a contractual/SLA obligation negotiated with an external supplier, making it a supplier management concern.

Option A (installing software) is a routine request fulfillment or operational IT task performed internally - no supplier relationship is being managed. Option B (improving application performance) falls under application management or continual improvement, which is an internal process focused on the software itself, not on governing an external supplier.

Memory tip: Think of Operational supplier management as anything involving "what a supplier must do for you" - especially around availability, continuity, and contract performance. If the activity involves managing an obligation from an external party (e.g., "you must provide X within Y time"), it's supplier management. If it's something your own team does to hardware or software, it belongs elsewhere.

Topics

#Operational supplier management#contingency planning#calamity response