BIMF.EN · Question #40
Which Management process is responsible for monitoring how many hours have been worked?
The correct answer is C. Planning and resource management. Planning and Resource Management (C) is correct because this process oversees the allocation and tracking of resources - including human resources and their working hours - ensuring that time spent aligns with project plans and budgets. Contract Management (A) focuses on…
Question
Which Management process is responsible for monitoring how many hours have been worked?
Options
- AContract management
- BFinancial management
- CPlanning and resource management
How the community answered
(28 responses)- A18% (5)
- B7% (2)
- C75% (21)
Explanation
Planning and Resource Management (C) is correct because this process oversees the allocation and tracking of resources - including human resources and their working hours - ensuring that time spent aligns with project plans and budgets.
Contract Management (A) focuses on negotiating, executing, and overseeing agreements with vendors or clients; it deals with contractual obligations, not internal time tracking.
Financial Management (B) handles budgets, costs, and financial reporting at a broader level; while it may consume hour-based data, it is not responsible for directly monitoring how many hours are worked.
Memory tip: Think of "Planning and Resource Management" as the process that answers "Who does what, for how long?" - hours worked are a resource metric, so they belong to the process that manages resources.