Who must always authorise a Request for Change before the change is built and tested?
The correct answer is C. The Change Manager. See the full explanation below for the reasoning.
Question
Who must always authorise a Request for Change before the change is built and tested?
Options
- AThe Configuration Manager
- BThe Change Initiator
- CThe Change Manager
- DRelease Management
How the community answered
(50 responses)- A8% (4)
- B4% (2)
- C70% (35)
- D18% (9)