nerdexam
BCS-ISEB

BH0-001 · Question #55

At what point should capacity requirements of a proposed system be first considered?

The correct answer is B. As early as possible. See the full explanation below for the reasoning.

Question

At what point should capacity requirements of a proposed system be first considered?

Options

  • ALeave it until the system is implemented and see if the system works O.K.
  • BAs early as possible
  • CWhen the Development Manager has completed testing and passes the system to Operations for
  • DJust before the system goes live

How the community answered

(23 responses)
  • A
    13% (3)
  • B
    74% (17)
  • C
    4% (1)
  • D
    9% (2)

Community Discussion

No community discussion yet for this question.

Full BH0-001 Practice