From a well-informed User's perspective, which of the following is a likely sequence in the management of a service failure?

The correct answer is B. Incident Management, Problem Management, Change Management, Release Management. See the full explanation below for the reasoning.

Question

From a well-informed User's perspective, which of the following is a likely sequence in the management of a service failure?

Options

  • AIncident Management, Problem Management, Release Management, Change Management
  • BIncident Management, Problem Management, Change Management, Release Management
  • CChange Management, Incident Management, Problem Management, Release Management
  • DIncident Management, Change Management, Release Management, Problem Management

How the community answered

(54 responses)
  • A
    4% (2)
  • B
    72% (39)
  • C
    15% (8)
  • D
    9% (5)