Possible problems with Change Management include:
The correct answer is C. Lack of ownership of impacted services. See the full explanation below for the reasoning.
Question
Possible problems with Change Management include:
Options
- AGreater ability to absorb a large volume of change
- BIncreased visibility and communication of changes
- CLack of ownership of impacted services
- DBetter alignment of IT services to actual business needs
How the community answered
(48 responses)- A2% (1)
- B15% (7)
- C77% (37)
- D6% (3)