In ITSCM, Risk Analysis has three elements used in the calculation to establish risk, which of the following is NOT one of them?

The correct answer is C. Impact. See the full explanation below for the reasoning.

Question

In ITSCM, Risk Analysis has three elements used in the calculation to establish risk, which of the following is NOT one of them?

Options

  • AAsset
  • BThreat
  • CImpact
  • DVulnerability

How the community answered

(27 responses)
  • A
    19% (5)
  • B
    4% (1)
  • C
    70% (19)
  • D
    7% (2)