AZ-400 · Question #463
You are creating a dashboard in Azure Boards. You need to visualize the time from when work starts on a work item until the work item is closed. Which type of widget should you use?
The correct answer is A. cycle time. https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead- time?view=azure-devops Both lead time and cycle time widgets are useful to teams. They both indicate how long it takes for work to flow through their development pipeline. Lead time measures the
Question
Options
- Acycle time
- Bvelocity
- Ccumulative flow
- Dlead time
How the community answered
(28 responses)- A93% (26)
- B4% (1)
- D4% (1)
Explanation
https://learn.microsoft.com/en-us/azure/devops/report/dashboards/cycle-time-and-lead- time?view=azure-devops Both lead time and cycle time widgets are useful to teams. They both indicate how long it takes for work to flow through their development pipeline. Lead time measures the total time elapsed from the creation of work items to their completion. Cycle time measures the time it takes for your team to complete work items once they begin actively working on them.
Community Discussion
No community discussion yet for this question.