A company wants to migrate workloads from on-premises to the cloud. What are the three main migration effort phases that you would advise the company to prepare for?

The correct answer is A. Release workloads C. Deploy workloads D. Assess workloads. Migration efforts based on Azure Cloud Adoption Framework include the incremental approaches to the workloads. Each migration iteration is a batch of migration waves - the smallest workload that produces tangible results. Usually, the iteration consists of the three phases…

Submitted by lukas.cz· Mar 6, 2026Design infrastructure solutions

Question

A company wants to migrate workloads from on-premises to the cloud. What are the three main migration effort phases that you would advise the company to prepare for?

Options

  • ARelease workloads
  • BLoad workloads
  • CDeploy workloads
  • DAssess workloads
  • ETest workloads

How the community answered

(29 responses)
  • A
    93% (27)
  • B
    3% (1)
  • E
    3% (1)

Explanation

Migration efforts based on Azure Cloud Adoption Framework include the incremental approaches to the workloads. Each migration iteration is a batch of migration waves - the smallest workload that produces tangible results. Usually, the iteration consists of the three phases: Assess workloads - these workloads help to evaluate costs, architecture, and deployment tools. Deploy workloads - these workloads replicate the current functionality in a cloud using lift and shift, lift, and optimize approaches. Release workloads - these workloads provide test, optimization, documentation, and release of the cloud migration efforts. https://docs.microsoft.com/en-us/azure/cloud-adoption-framework/migrate/ https://docs.microsoft.com/en-us/azure/cloud-adoption-framework/migrate/#migration-effort