ASF · Question #62
A 200 member project team is working on a large and complex system with multiple sub-systems. They would like to start using the Agile Scrum methodology. As a Scrum Master, what would your best…
The correct answer is C. Agree a logical sub-division of the system so that smaller Scrum teams can work on sub- systems. C is correct because Scrum explicitly supports large projects through the "Scrum of Scrums" pattern - splitting a large team into multiple smaller Scrum teams (typically 5–9 members each), each owning a sub-system, then coordinating across teams. This preserves Scrum's core…
Question
A 200 member project team is working on a large and complex system with multiple sub-systems. They would like to start using the Agile Scrum methodology. As a Scrum Master, what would your best advice be?
Options
- AScrum is not suited for such a large project.
- BAsk all potential members of the project team to have a meeting first and decide if they agree to
- CAgree a logical sub-division of the system so that smaller Scrum teams can work on sub- systems
How the community answered
(22 responses)- A9% (2)
- B18% (4)
- C73% (16)
Explanation
C is correct because Scrum explicitly supports large projects through the "Scrum of Scrums" pattern - splitting a large team into multiple smaller Scrum teams (typically 5–9 members each), each owning a sub-system, then coordinating across teams. This preserves Scrum's core values while scaling to enterprise size.
A is wrong because Scrum is not inherently limited to small projects. Scaled frameworks like SAFe, LeSS, and Nexus are built precisely for this scenario - large teams using Scrum across complex systems.
B is wrong because consensus from all 200 members is neither practical nor a Scrum principle. The Scrum Master's role is to guide and coach, not to seek unanimous approval before adopting a methodology.
Memory tip: Think "Divide and Scrum" - when a team is too large for one Scrum, divide the system into sub-systems and let smaller Scrum teams own each piece. Large team = multiple Scrums, not no Scrum.
Topics
Community Discussion
No community discussion yet for this question.