A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three…

The correct answer is B. Points are assigned for the overall Story, not for parts of the Story. In Planning Poker, Story points represent the total effort for the entire Story as a team, not a sum of individual role-based estimates - the Developers' 2 points and Testers' 3 points should have been discussed and converged into a single shared number, not added together…

Scrum Developer Role

Question

A team estimates a Story using the Planning Poker technique. The team decides to allocate five Story points to the Story, because the Developers estimated two points and the Testers estimated three points. Which statement is true regarding this scenario?

Options

  • APoints are assigned by the Scrum Master, not by the team.
  • BPoints are assigned for the overall Story, not for parts of the Story.
  • CPoints are never estimated, but always determined beforehand.
  • DThe team forgets to ask the Product Owner about the estimate.

How the community answered

(40 responses)
  • A
    3% (1)
  • B
    90% (36)
  • C
    5% (2)
  • D
    3% (1)

Explanation

In Planning Poker, Story points represent the total effort for the entire Story as a team, not a sum of individual role-based estimates - the Developers' 2 points and Testers' 3 points should have been discussed and converged into a single shared number, not added together, making B correct.

Why the distractors are wrong:

  • A is wrong because in Scrum, the Scrum Master facilitates but never assigns estimates - only the Developers (the whole team doing the work) estimate.
  • C is wrong because estimation is an inherent part of Planning Poker and Sprint Planning; points are not predetermined.
  • D is wrong because the Product Owner clarifies the Story but does not participate in the estimate itself.

Memory tip: Think of Story points like rating a movie as a group - you don't average the critic's score and the audience's score separately; you discuss and land on one collective rating for the whole film.

Topics

#Planning Poker#Story Points#estimation#whole story