A large product team features six different teams having ten members each, working on a project that involves four high level features. How many Product Backlogs should the team have?

The correct answer is A. 1. In Scrum, there is always one Product Backlog per product - regardless of how many teams are working on it or how many features it contains, because a single backlog ensures a unified, prioritized view of all work and prevents duplication or misalignment across teams. Option B…

Scaling Scrum

Question

A large product team features six different teams having ten members each, working on a project that involves four high level features. How many Product Backlogs should the team have?

Options

  • A1
  • B4
  • C6

How the community answered

(33 responses)
  • A
    94% (31)
  • B
    3% (1)
  • C
    3% (1)

Explanation

In Scrum, there is always one Product Backlog per product - regardless of how many teams are working on it or how many features it contains, because a single backlog ensures a unified, prioritized view of all work and prevents duplication or misalignment across teams. Option B (4) is wrong because the number of high-level features does not determine the number of backlogs; features are simply items or epics within the one backlog. Option C (6) is wrong because having six teams does not mean six backlogs - multiple Scrum teams working on the same product all draw from the same single backlog, which is owned by one Product Owner. A helpful memory tip: "One product = one Product Backlog" - anchor the count to the product, not the teams or features, and you'll never get this wrong on the exam.

Topics

#Product Backlog#multiple teams#single backlog#scaled Scrum