AGILEPM-PRACTITIONER · Question #24
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox Plan for Timebox B?
The correct answer is B. Team Leader. In DSDM (Agile Project Framework), the Team Leader owns day-to-day management of the team's work, which includes maintaining and updating the Timebox Plan - so once a change of priority is approved at a higher level, it falls to the Team Leader to incorporate the new…
Question
Once the change of priority has been approved, who is then responsible for including the requirement for a secondary exit from the upstairs of the building to the Timebox Plan for Timebox B?
Options
- AMarketing Director, in the role of Business Visionary.
- BTeam Leader.
- CProject Manager and Architect, in the role of Technical Co-ordinator.
- DArchitecture Angels' Senior Management Team.
How the community answered
(28 responses)- A4% (1)
- B93% (26)
- D4% (1)
Explanation
In DSDM (Agile Project Framework), the Team Leader owns day-to-day management of the team's work, which includes maintaining and updating the Timebox Plan - so once a change of priority is approved at a higher level, it falls to the Team Leader to incorporate the new requirement (the secondary exit) into Timebox B's plan.
Why the distractors are wrong:
- A (Business Visionary/Marketing Director): The Business Visionary approves business priorities and provides vision, but does not own detailed Timebox planning - that's an operational, not strategic, responsibility.
- C (Technical Co-ordinator): The Technical Co-ordinator ensures architectural integrity and technical standards; they do not manage the day-to-day Timebox Plan.
- D (Senior Management Team): Senior management may have triggered or approved the priority change, but their role ends at governance - execution and planning responsibility passes down to the Team Leader.
Memory tip: Think of the Team Leader as the "quarterback" - others call the play (approve the change), but the Team Leader is responsible for running it by updating the plan and directing the team.
Topics