What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

The correct answer is C. The Business Visionary, Business Sponsor and Solution Development Team should reassess the. C . The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities. In Agile Project Management, priorities are often reassessed and reprioritized based on new information or changes in the project's…

Evolutionary Development

Question

What should be done to allow the requirement for a secondary exit from the upstairs of the building to be changed into a Must Have priority and moved into Timebox B?

Options

  • AThe Project Manager should extend the timescale of Timebox B and shorten Timebox C.
  • BThe Solution Development Team should change a Must Have requirement into a Should Have in
  • CThe Business Visionary, Business Sponsor and Solution Development Team should reassess the
  • DThe Project Manager should move a Must Have requirement from Timebox B into Timebox C.

How the community answered

(25 responses)
  • A
    8% (2)
  • B
    20% (5)
  • C
    68% (17)
  • D
    4% (1)

Explanation

C . The Business Visionary, Business Sponsor and Solution Development Team should reassess the Prioritised Requirements List and its priorities. In Agile Project Management, priorities are often reassessed and reprioritized based on new information or changes in the project's context. The need for a secondary exit due to compliance with fire safety regulations would necessitate such a reassessment. The Business Visionary and Business Sponsor, who provide the vision and funding for the project, together with the Solution Development Team, who are responsible for implementing solutions, should collaboratively review the Prioritised Requirements List to reflect this new priority. This change must be agreed upon by these key stakeholders to ensure that it aligns with the business needs and project goals.

Topics

#Change Management#MoSCoW Reprioritisation#Timebox Planning#Requirements Change