AGILEPM-PRACTITIONER · Question #23
Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the project in the Prioritised…
The correct answer is D. Architecture Angels' Senior Management Team. The Senior Management Team, which includes the roles of the Sales, Marketing, and Finance Directors, and the Chief Executive, is typically responsible for steering the project and making decisions that reflect the overall scope and objectives of the project. They would be the…
Question
Who is responsible for approving that the change in priority of the requirement for a secondary exit from the upstairs of the building accurately reflects the scope of the project in the Prioritised Requirements List?
Options
- AMarketing Director, in the role of Business Visionary.
- BProject Manager and Solution Development Team.
- CProject Manager and Architect, in the role of Technical Co-ordinator.
- DArchitecture Angels' Senior Management Team.
How the community answered
(25 responses)- A12% (3)
- B8% (2)
- D80% (20)
Explanation
The Senior Management Team, which includes the roles of the Sales, Marketing, and Finance Directors, and the Chief Executive, is typically responsible for steering the project and making decisions that reflect the overall scope and objectives of the project. They would be the appropriate body to approve changes in the project scope as represented in the Prioritised Requirements List, especially for a requirement that has legal and safety implications, such as a secondary fire exit. This team would ensure that such a change aligns with the strategic goals and compliance requirements