AD0-E907 · Question #71
A project manager notices that several high-priority tasks are delayed due to resource constraints. How can they resolve this issue?
The correct answer is B. Adjust task priorities in the resource planner. Adjusting task priorities in the resource planner (B) directly addresses the root cause: resources are misallocated or overcommitted. By reprioritizing, the project manager ensures constrained resources flow first to the highest-priority work without requiring external changes…
Question
A project manager notices that several high-priority tasks are delayed due to resource constraints. How can they resolve this issue?
Options
- AExtend project deadlines to accommodate delays
- BAdjust task priorities in the resource planner
- CAdd more team members to the resource pool
- DReduce the project scope
How the community answered
(37 responses)- A3% (1)
- B73% (27)
- C16% (6)
- D8% (3)
Explanation
Adjusting task priorities in the resource planner (B) directly addresses the root cause: resources are misallocated or overcommitted. By reprioritizing, the project manager ensures constrained resources flow first to the highest-priority work without requiring external changes to the project.
Why the distractors fail:
- A (Extend deadlines) treats the symptom, not the cause - delays will recur if the underlying resource conflict isn't resolved.
- C (Add team members) may help long-term but introduces ramp-up time and coordination overhead, and isn't always an option within budget or hiring constraints.
- D (Reduce scope) is a last resort that sacrifices deliverables, not a first response to a scheduling conflict.
Memory tip: Think of the resource planner as a traffic controller - when congestion hits, you reroute (reprioritize), you don't just build more roads (add people) or close destinations (cut scope).