Which step must be performed immediately after powering off the device when replacing a Cisco chassis?
The correct answer is D. Label and remove all I/O cables. After powering off a Cisco device in preparation for chassis replacement, the immediate next step is to label and remove all I/O cables. This step is crucial to ensure that all connections can be accurately restored after the new chassis is installed. Proper labeling prevents…
Question
Which step must be performed immediately after powering off the device when replacing a Cisco chassis?
Options
- ARemove the chassis ground.
- BBack up the device configuration.
- CRemove the chassis.
- DLabel and remove all I/O cables.
How the community answered
(46 responses)- A2% (1)
- B2% (1)
- C4% (2)
- D91% (42)
Explanation
After powering off a Cisco device in preparation for chassis replacement, the immediate next step is to label and remove all I/O cables. This step is crucial to ensure that all connections can be accurately restored after the new chassis is installed. Proper labeling prevents confusion and potential misconfigurations during reassembly. Only after all cables are safely disconnected should you proceed to remove the chassis ground and then the