nerdexam
Microsoft

74-344 · Question #96

You are a portfolio manager for an organization that uses Project Server 2013. You plan to create several portfolio reports for the executive team. You need to ensure that your first report shows a…

The correct answer is B. Create a Pivot Table in Microsoft Excel that gets data from the OLAP Portfolio Analyzer data. See the full explanation below for the reasoning.

Question

You are a portfolio manager for an organization that uses Project Server 2013. You plan to create several portfolio reports for the executive team. You need to ensure that your first report shows a list of all projects in your organization with timephased information regarding how the Actual Work and the Actual Cost have varied on a monthly basis. What should you do?

Options

  • ACreate a Project Center view with the following project fields: Name, Start Date, Finish Date,
  • BCreate a Pivot Table in Microsoft Excel that gets data from the OLAP Portfolio Analyzer data
  • CCreate a Project Center view with the following project fields: Name, Start Date, Finish Date,
  • DCreate a Pivot Table in Microsoft Excel that gets data from the Project Server-Simple Projects

How the community answered

(59 responses)
  • A
    17% (10)
  • B
    73% (43)
  • C
    7% (4)
  • D
    3% (2)

Community Discussion

No community discussion yet for this question.

Full 74-344 Practice